Muni Metro to Launch Double-Train Loading, Three-Car Trains in October

Photo: ##http://www.flickr.com/photos/robvillanueva/6815095381/in/photostream/##RobVSF/Flickr##

Muni is poised to begin double-train loading and running three-car trains at underground metro stations to speed up boarding and increase capacity on the system’s busiest stretch.

As we reported, Muni began testing double-train loading, a.k.a. “double berthing,” in July, but Transit Director John Haley said the agency hasn’t run tests with actual trains yet. Managers have upgraded the train control software, which Muni says is the main hurdle to allowing two trains to board passengers in a station simultaneously, and run simulations.

“The tests on the software so far have been positive with no bugs or glitches found,” Haley told Streetsblog in an email. “The software and hardware are installed and if the Live Field tests go well we would target Late October / early November to start in service.”

“We think the public will love it,” he added.

Meanwhile, Haley told a Board of Supervisors committee last week that Muni plans to start running three-car trains to make short runs within the underground system only, between the Embarcadero and West Portal Stations, to relieve crowding. Haley said Muni had to work out software kinks to ensure that the third car would communicate with the others, and that those trains should begin running by next month.

Those service upgrades are among eight changes that Haley said Muni operations managers are looking to make. See the rest on the table below.

Image: SFMTA

ALSO ON STREETSBLOG

Muni Plans to Launch “Double Berthing” in October, a Year Behind Schedule

|
Muni still hasn’t launched double loading of trains in its metro stations, a.k.a. “double berthing,” but says it could finally happen in October — a full year after the original launch date. “The project is still in testing, to debug issues with the platform signs and trains,” said Muni Operations Director John Haley. “According to […]

Muni to Test Double-Train Loading in Metro Stations This July

|
Muni will test out a method to improve metro operations this July, letting two trains load passengers on the same platform simultaneously, according to SFMTA spokesperson Paul Rose. Few details on the test run are available, but Muni officials have discussed making the change for several years as a way to reduce back-ups in the […]

Muni Double-Berthing Still Delayed Pending CPUC Approval

|
The ongoing delays for double-berthing in Muni Metro stations continue, as Muni waits for its training plan to be approved by the CA Public Utilities Commission. After Muni officials demonstrated double-berthing for the CPUC in December, expecting the green light, Muni Operations Director John Haley told Streetsblog that CPUC needed to sign off its training plan, […]