Muni Pushes “Double Berthing” Launch Back One More Week

Photo: RobVSF/Flickr

We’ve now lost count of how many times Muni has delayed the launch of “double berthing” in its Metro stations. Last we heard, it was promised to launch tomorrow, but the agency now says it needs one more week of testing before two trains can simultaneously board on the same platform.

“We are adding an additional test for double boarding — to ensure that our live test plan is as thorough as possible, and our signal mechanics have more time with the program and infrastructure,” said SFMTA spokesperson Paul Rose. The live test that was planned for early morning last Saturday, a demonstration which will allow CA Public Utilities Commission officials to sign off on the launch, will instead happen early tomorrow morning.

“We are hopeful that we will receive certification from CPUC soon after that, to implement this feature into regular service,” said Rose. If all goes as planned (and it will, right?), the change would go into effect on Saturday, December 20.

ALSO ON STREETSBLOG

Muni Double-Berthing Still Delayed Pending CPUC Approval

|
The ongoing delays for double-berthing in Muni Metro stations continue, as Muni waits for its training plan to be approved by the CA Public Utilities Commission. After Muni officials demonstrated double-berthing for the CPUC in December, expecting the green light, Muni Operations Director John Haley told Streetsblog that CPUC needed to sign off its training plan, […]

Muni Metro to Launch Double-Train Loading, Three-Car Trains in October

|
Muni is poised to begin double-train loading and running three-car trains at underground metro stations to speed up boarding and increase capacity on the system’s busiest stretch. As we reported, Muni began testing double-train loading, a.k.a. “double berthing,” in July, but Transit Director John Haley said the agency hasn’t run tests with actual trains yet. […]

Muni “Double Berthing” on Hold Two to Four Weeks, Pending CPUC Approval

|
Muni may finally launch “double berthing” in its Metro stations in two to four weeks, “barring anything we can’t think of,” according to Muni Operations Director John Haley. Muni riders were first promised simultaneous loading of two trains in underground stations in October 2013. More recently, the launch was scheduled for December, then delayed again. Muni demonstrated a live test on […]